What Happens Next
RTMSD must obtain agency approvals & permits - PennDOT, PA Department of Environmental Resources (stormwater), County Conservation District, utilities (sewer, water, electric), & emergency-services reviews.
Middletown Township Council – RTMSD must revise & resubmit final engineering & traffic materials & address the 31 conditions.
The final plan will go before the Planning commission & then to Council. Council has the final say.
School district estimates 6-8 months before the final land development application is before Council for approval.


This is NOT a Quick Fix


Act 34 of 1973 (Act 34) - part of the Pennsylvania Public School Code governing how public-school districts can finance & approve new school construction projects.
An Act 34 project requires a referendum (vote of the electors) if the Maximum Building Construction Cost exceeds the Aggregate Building Expenditure Standard.
School district says it does not, that is, a referendum is not required.
The Act 34 hearing is planned for March 2027

Email worktogetherrtmsd@gmail.com to stay informed, ask questions, receive updates.