About the Land Development Application:
The constrained parcel size relative to the intensity of the proposed development raises serious public safety, traffic, & environmental stewardship concerns.
All calculations are underestimated, there are a number of inaccuracies, missing information & flawed assumptions; existing traffic conditions are not described.
Traffic monitoring was conducted manually on a single day - the Wednesday after Memorial Day - for 1 hour in the Am and 1 in the PM - but not the times working parents will arrive.
Daily vehicle trips generated by the proposed K-1 is 1,861 - yet the value underestimates student capacity & fails to include the 105 staff.
The proposed K-1 site can accommodate a 44-car queue, which the school district, not the traffic engineer, determined acceptable.
The remaining 250+ parent vehicles will spillover onto Rose Tree Road and Route 352.
The study concludes traffic conditions are acceptable “only in conjunction with future PennDOT improvements” which are said to be a decade away.
The planned, district lead, Rose Tree Road realignment is up to $3.7M & will address existing traffic - not the additional traffic from the proposed land development.
No analysis was done regarding whether emergency vehicles can bypass the lengthy car queue or how the site will function in inclement weather /mass early dismissal scenario.
A regional K-1 requires additional bus runs and significantly more private vehicle trips, elevating energy usage and greenhouse gas emissions, contributing to climate change, heat island generation, and air pollution.
Critical information regarding groundwater, wetlands, turf materials, lighting, & the protection of neighbors’ drinking water wells is missing.
Rezoning the property to count high school athletic fields in the stormwater calculation gives the appearance of ordinance compliance by changing the math, not the science, & is not protective of the Ridley Creek watershed.
236 trees will be removed. “The School District intends to pay a fee in lieu of planting the required number of replacement trees” to create an “open grass environment.”
Displacement of wildlife, removal of trees & destruction of open space is not the only choice. Both Glenwood & Rose Tree Elementary schools have ample school owned and zoned “open grass” acreage to build the same 6 classroom, 2 story building planned for the middle school, said to have “no traffic impact” which will solve stated needs. The intentional destruction of the open space & harm to the watershed is completely unnecessary.
The small parcel does not appear to have a sidewalk or outdoor playground - for full day kindergarten & first graders? The school superintendent said K-1 Centers are held to a different playground area standard; it is not understood what that means but the possibility that there is no outdoor recess or play area is an added concern.
The lighting map lacks key details, including number of fixtures, pole heights, fixture types, bulb types, light levels, shielding, light levels projected at adjacent property lines, and operating hours.
This William Penn Land Grant property dates to 1702. Penncrest High School is named after the historic Penncrest Farms & part of the high school property was originally part of the 18th-century farmstead owned by prominent Philadelphia architect Walter Smedley. A 2024 PennDOT presentation identifies portions of the proposed K-1 parcel as historic property.
Further details and specifics are available in Comments to the Township and Comment to PennDOT - linked here.
In other news, the below linked 2018 Capacity Feasibility Study was available on-line. It was noted that pages 28-31 are missing. A version of the Study including missing pages consisting of Pros/Cons & costs was located. There are discrepancies with the page titled “Options Considered, Not Recommended” - see the Missing Pages tab for more information.
From the June 2026 Work Session - “The construction market is facing several headwinds that could impact the budget.”
For the 2026/2027 school year, Media Elementary will have 3 first grade classrooms instead of the current 4.
May 2026 Land Development Update
· Eminent domain claim filed May 1, 2026 to take adjacent church property for Rose Tree Road realignment;
· “Preliminary” Land Development Application submitted to Middletown Township May 6, 2026;
· Environmental Impact Assessment Report omitted from application & submitted May 22, 2026.
· According the District, the Township’s decision is anticipated in spring 2027.
Documents are available on Middletown Township website under Ongoing Projects https://middletowndelcopa.gov/
A summary of the application is on the Updates & News page
Details & specifics are available in Comments to the Township and Comment to PennDOT - linked here
Township Comments on the application - linked here
RTMSD Response - linked here
RTMSD Traffic Engineer Response -linked hereWrite your text here...
October 7, 2026 Council Meeting
As with prior meetings, the school district’s presentation was a series of half-truths beginning with the scope of the proposed “K-1 Center.” Although the superintendent mentioned the 18-21 year adult students, he failed to say that the 9th-12th grade high school students in the autistic program will be moved to this school as well.
State grants are not “free money.” It is taxpayer money.
Enrollment:
· 2026/27 enrollment data shows Glenwood Elementary is down by 15 students and Indian Lane is less 11 disproving the mantra that more homes equate to more students.
· This year, Media Elementary reduced 1st grade from 4 grades to 3 this year.
· At the May 2026 school board meeting, a presenter said they looked at the number of registrations received for kindergarten & class size & are able to address the teacher need at Rose Tree elementary through a staff transfer. It was stated “class size is still very favorable across the elementary classrooms even with that one move.” A clarifying question was asked by a Board member. The answer: “We really have what we consider to be favorable class sizes. So class sizes are not going up.”
Traffic: · The traffic is here now; the road system cannot not sustain 1861 additional vehicle trips. · The traffic engineer said the C rated level of service intersections will go to D and the D’s will go to F as a result of the proposed K-1. This is currently rated as C.
https://drive.google.com/file/d/1hA14-EdPYRzEMWVmvtXRWlSGLm7sdRAG/view
· The traffic study states traffic conditions are acceptable only if future PennDOT improvements - currently in preliminary engineering and a decade or more away - are completed.
· PennDOT has a major highway improvement project planned to address area traffic. The proposed school traffic would create a moving target for trying to solve the existing traffic deficiencies.
· The school district owns acres of “open-grass” land upon which they could build a new wing or add a 2nd floor. Such a common-sense solution would be safer, generate less traffic, accomplished sooner, at a lower cost, keeps the youngest students close to home and among familiar faces, children can walk - there are 255 in the AM and 135 in the PM who currently walk - the land is already the desired "open grass," the environmental harm would be minimized, and there will be money for other needed upgrades thus providing equity.
· The newly proposed 141, double stacked carline which is said to exceed the demand by 6 car lengths, fails to account for the 255 children who currently walk in the AM and the 135 who walk in the PM.
Township Comprehensive Plan and Zoning ordinance Requirements: · The proposal conflicts with the Township’s Comprehensive Plan and Parks, Recreation, and Open Space Plan, including goals for stormwater management, traffic mitigation, open-space preservation, neighborhood integrity, historic and natural resources protection, schools, and the Township’s expressed vision for responsible growth. · The Comprehensive Plan identifies traffic congestion as a critical issue & calls to reduce pedestrian conflicts, unnecessary turning movements, congestion, & cut-through traffic. The Township Plan calls for maintaining the character & integrity of existing residential neighborhoods. The proposed K-1 directly contradicts these established planning objectives, threatening the safety, livability, and residential character the Township’s Comprehensive Plan seeks to protect. · The Comprehensive Plan & Township ordinance recognize the importance of a 50-foot riparian buffer. The school district seeks a waiver & claims it should be granted since it’s been granted elsewhere.
Compliance with other ordinance requirements is questioned:
· § 275- 150. (d) Maximum total impervious surface area: 35%.
· § 210-28(B)(1) requires pedestrian walkways along both sides of new roads and along parking compounds in all land developments.
· § 275- 150(e) Maximum building coverage: 15%. Compliance is not determined or demonstrated.
· §275-150(A)(6) requires automobile and school-bus stacking lanes be sufficient and that stacking lanes and waiting areas to be clearly marked and not be shared with parking circulation aisles, traffic flow, or pedestrian circulation areas.
· §275-150(A)(7) The traffic impact study did not analyze the traffic generation from the proposed use/development and its potential impact on the surrounding road system. An assessment and plan for the circulation of pedestrians and users within and near the proposed use and lot shall be included.
· § 275-163(A)(1): Woodlands and Trees. No more than 50% of the woodlands may be disturbed on a parcel (school district calculation includes the Penncrest parcel too).
· § 275-168 the parking requirement is: 2 spaces per 1,000 square feet of classroom area, plus 12 per 1,000 square feet of assembly room area. How is 199 spaces adequate for 105 staff and an 820-capacity school?
· § 275-135 Outdoor Lighting
· Noise Impacts - not measured
Other: • the school district answered that staff were included in the 599-vehicle trip value. 47 staff of the 105 were included. •The school district stated the proposed K-1 prevents re-districting. Other than the Middletown Township students, all the K-1 students would be redistricted and redistricted again after 1st grade. • A question was asked regarding use of the building structures – Answer given – “yes.” A similar question was asked at a school board meeting. The architect answered “no” explaining everything is designed for 5, 6, 7-year-olds – furniture, water fountains, bathrooms. Also, the gymnasium will be rented. • 2018 Capacity study showed minor upgrades and expansions to address crowding. 2023 Updated Capacity study looked at libraries, expanding cafeterias, adding bathrooms. It’s been learned that the district removed pages 28–31 of the 2018 Study – the pros, cons and costs. • How much time will the carline take? a question the residents have repeatedly asked and the district continues to refuse to answer. A guesstimate for how long the elementary schools take was provided. The problem can be modeled and an answer generated, but the district does not want the Council or public to know because it is too long. The proposed school is kindergarten and 1st grade – all in car seats taking much more time than the elementary schools. It is critical information needed for an informed decision.
Another Important Question
The district acknowledges that the project will be financed with debt & that debt service will come from the operating budget. What will this project cost our school district over the next 20 or 30 years?
Annual operating costs remain undisclosed despite asking.


Background
Full day kindergarten is not the issue.
The school board’s lack of objective analysis, transparency, meaningful engagement with the community & a commitment to a plan even if it is not a safe solution is why the proposed regional K-1 siting is a source of conflict rather than a community asset.
· Parents deserve timely resolution to problems.
· Taxpayers deserve responsible stewardship of their money.
· Every school in the district deserves equitable consideration.
· Every child deserves to learn in a safe school.
· The environment deserves protection.
1. Safety: A child’s first school experience should be enjoyable. The proposed K-1 is a regional school, separating very young children from siblings & familiar faces, far from most homes, with accessibly complicated by traffic & safety & outdoor play area compromised by site constraints.
Picking up & dropping off a child at school should be an exciting, fun occasion, not a burdensome task for parents & caregivers.
2. Timing: Families need full-day kindergarten now. Road realignment, construction, legal actions, permits & approvals mean years of planning still ahead. The district could choose to prioritize full-day kindergarten & provide it faster.
3. Cost: Money spent on consultants, lawyers, road construction would be better invested on the children & education. Full-day kindergarten can be accomplished without a $92M+ solution that creates decades of debt & inequity among schools.
4. The project is much bigger than "full-day kindergarten." The proposed regional school with have 5–7-year-olds, the Linking Learning to Life program serving students ages 18-21 with special needs & the 9th-12th grade autism program - more like 3 schools in a single building that is larger than the YMCA on Route 1.
September 8, 2026 Planning Commission Meeting
Middletown Township Planning Commission voted 4–2 to recommend approval of the preliminary plan for the proposed regional K-1 Center & multi-sport complex with a list of conditions but without resolving the serious questions surrounding traffic, safety, site design, environmental impacts or the project's long-term consequences.
Decision on the preliminary plan now goes to Township Council.
Traffic -Background
· The District's Transportation Study estimates 1,861 weekday vehicle trips (vehicle trip is in or out of a site) with 261 cars estimated entering during the AM peak hour.
· Previously a 44 on-site car line storage queue was presented.
· The Transportation Study:
· Deviated from industry standards. Manual monitoring was conducted on only one day - the Wednesday after Memorial Day - for just 1 hour in the morning, 8:15–9:15, & 1 hour in the afternoon, 3:15–4:15:
· Data collection times do not reflect schedules of working parents & the before- and after care program;
· Traffic conditions are acceptable only if future PennDOT improvements are completed;
· Does not analyze the multi-sport complex after school & weekend traffic or overlap usage.
· The consultant concluded the proposed regional K-1 & high school traffic will not coincide. However, many Penncrest students start later than 7:30 due to “block scheduling.” Since there is one bus run, the students either drive or are dropped off. This additional traffic overlap is not considered.
September 8, 2026 Meeting Recap:
The district proposed double-stacking cars to increase the queue to141 with no calculation showing the maximum number of vehicles expected in the queue simultaneously or vehicle-processing rate. Young children require a slower, more controlled loading/unloading process.
Students: The school was again described as serving 5 -7-year-olds with no mention of inclusion of the Linking Learning to Life program serving students ages 18-21 with special needs & the 9th-12th grade autism program.
Athletics: The superintendent spoke about the baseball-field orientation even though there is no issue & did not address the question of the girls' softball field orientation.
Lighting: The superintendent stated a 420-foot distance exists between the lights & residents which does not consider the full multi-sport complex field & pathway lighting plan.
Geothermal: The Township raised concerns about the potential impact of geothermal installation on nearby private drinking-water wells. The consultant responded by explaining why it selected geothermal leaving the concern unanswered.
Riparian buffer: The project requires a riparian buffer waiver. In response to concerns, the consultant pointed to other projects where the Township granted similar waivers without explaining why the waiver is necessary & alternatives considered.
Longview Park: Is not simply an unrelated neighboring property; rather, because of site deficiencies, it is being integrated into the proposed project’s design to address turning movement conflicts, traffic circulation problems, & pedestrian movement.
The public is told the school district will not use the park while at the same time the Township is considering a pedestrian connection & measures to prevent unauthorized parking.
Pedestrians: Site constraints result in pedestrian safety risks which parking restrictions do not eliminate. A proposed park connection does not make crossing Rose Tree Road safe.
August 14, 2026 Planning Commission Mtg
Meeting Recap: Everyone supports full-day kindergarten & investment in education.
Over 100 residents attended the August 11, 2026 Middletown Township Planning Commission Meeting - Traffic was the agenda topic.
Significant safety concerns were raised:
· A 44-car queue for 1,000 anticipated vehicles;
· Encouraging people to park at Long View Park & cross Rose Tree Road due to insufficient car queue & parking is not only dangerous, it is an illegal use of the open space per PA State Law;
· No sidewalks – seemingly an inability to add them;
· An undersized playground adjacent to the diesel bus queue (5 & 6-year-olds’ lungs are still developing & they breathe more rapidly);
· No analysis of emergency response capability around vehicle queues;
· Dangerous conditions on Rose Tree Road heightened during inclement weather;
· Overlap use of the entrance/exit by sporting-event traffic & high-school students (children ages 5-7 are among the least able to judge vehicle speed & gaps in traffic);
· An unmanaged cut-through road connecting Barren Road & Rose Tree Road;
· Creation of neighborhood cut-throughs contrary to Township Comprehensive Plan & Council campaign promises;
· An unmitigated traffic operational deficiency at Barren Road & Route 352;
· An area crash rate above the statewide average, PennDOT reports 82% of Route 352 crashes are rear-end collisions;
· Route 352 may be widened to 4 lanes increasing traffic speeds, heavy vehicle volume, traffic-related air pollution, & limiting access during construction.
38 people spoke, 5 in favor, 33 against the location of the proposed K-1 Center
The meeting concluded with the Township asking the School District if they wanted to request an extension, delaying the Planning Commission’s vote & allowing more time for the district to address concerns.
If no extension was requested, procedurally, the Planning Commission would have had to vote at Tuesday’s meeting. An extension request was verbally made. Inquirer article - linked here
July 14, 2026 Planning Commission Mtg.
Meeting Recap: Everyone supports full-day kindergarten & investment in education.
Residents expressed concerns about:
Safety and traffic
Taxes
Environmental impacts
Consistency with the Township Comprehensive Plan
Long-term impacts on the community
The superintendent addressed both the proposed K-1 Early Learning Center & planned multi-sport complex.
"K–1 Early Learning Center" Does Not Tell the Full Story
The proposed building would serve:
Children ages 5–7
Adults ages 18–21
High school students (grades 9–12) in autistic support programs
More like 3 schools in a single building.
Existing School Land
The superintendent emphasized that the district owns this property & does not own the alternative sites suggested. Not discussed - the district already owns 200 or more buildable acres of school zoned, “open grass environment” – which is what the school district wants to turn this woodland & meadow into - & is why they are willing to pay a fee rather than replace the hundreds of trees killed.
Rose Tree Road Property
Also not discussed - the Rose Tree Road parcel was never publicly offered for sale, despite statements made to the contrary. The property was acquired under the threat of eminent domain. The $5 million acquisition should be included in the total project cost.
Long View Park
A reference was made to connecting the school property to Long View Park.
Middletown residents oppose this concept; the site is too small for the proposed intensity & should not be permitted to dangerously spill onto Rose Tree Road or encroach on resident-purchased, Long View Park.
PennDOT Timeline
According to PennDOT meeting minutes, the environmental review for the entire PennDOT US 1 Route 352 Improvements must be completed before Rose Tree Road realignment can advance creating a high probability the Aug 2029 start will be missed.
Upcoming Legislative Meetings:
September 24, 2026
October 22, 2026
November 19, 2026
December 10, 2026
January 28, 2027
February 25, 2027
March 18, 2027
April 22, 2027
May 27, 2027
June 10, 2027
What happens at a School Board Legislative Meeting? Legislative Meetings are the business meetings of the Board. The agenda includes matters that require the vote of the School Board. Seated with the Board at the conference table are the Superintendent of Schools, the District Solicitor, the Board Secretary, and Student Liaisons. All items brought before the Board for vote have been presented or discussed at the Board’s Work Sessions or Executive Session meetings. (RTMSC website)
Upcoming Work Session Meetings:
September 10, 2026
October 8, 2026
November 12, 2026
December 1, 2026
January 14, 2027
February 11, 2027
March 11, 2027
April 8, 2027
May 13, 2027
June 3, 2027
What happens at a School Board Work Session? Work Sessions are the planning and discussion meetings of the Board. The Superintendent and Administration provide information regarding the management of the School District and items to be considered for approval at upcoming Legislative Meetings. (RTMSC website)
Council Workshop: January 7, February 4, March 4, April 1, May 6, June 3, July 1, August 5, September 2, October 7, November 4
Council Meetings: January 21, February 18, March 18, April 15, May 20, June 17, July 15, August 19, September 16, October 21, November 18, December 2
Reorganization Meeting 2027:
(Monday) January 4 at 8:00 PM